$55M cut threatens Hawai’i Convention Center leak fixes

Allison Schaefers
JAMM AQUINO / JAQUINO@STARADVERTISER.COM
                                Jeff Carbaugh, associate director of projects at the Hawai‘i Convention Center, hovers over two escalators Friday in the process of being replaced.
1/2
Swipe or click to see more

JAMM AQUINO / JAQUINO@STARADVERTISER.COM

Jeff Carbaugh, associate director of projects at the Hawai‘i Convention Center, hovers over two escalators Friday in the process of being replaced.

JAMM AQUINO / JAQUINO@STARADVERTISER.COM
                                Work continued Friday on the rooftop at the Hawai‘i Convention Center.
2/2
Swipe or click to see more

JAMM AQUINO / JAQUINO@STARADVERTISER.COM

Work continued Friday on the rooftop at the Hawai‘i Convention Center.

JAMM AQUINO / JAQUINO@STARADVERTISER.COM
                                Jeff Carbaugh, associate director of projects at the Hawai‘i Convention Center, hovers over two escalators Friday in the process of being replaced.
JAMM AQUINO / JAQUINO@STARADVERTISER.COM
                                Work continued Friday on the rooftop at the Hawai‘i Convention Center.

The Hawai‘i Convention Center’s two-year construction-­related shutdown may not resolve its decades‑old leak problems if lawmakers uphold a proposed $55 million funding cut, raising the likelihood the center will reopen in 2028 with ongoing water intrusion and safety concerns.

The House Finance Committee recently removed the request from its draft supplemental budget, despite warnings from center officials and the Hawai‘i Tourism Authority that the money is needed to complete other major leak‑­related repairs during the shutdown, which began Jan. 2 when Swinerton started construction.

The cut underscores broader concerns about escalating costs, shifting project scopes and oversight at the state‑owned convention center, which has struggled with worsening leaks since shortly after opening in 1998.

Lawmakers previously approved $100 million for capital improvements, including $64 million for rooftop terrace deck repairs and contingencies and $36 million for other projects. But General Manager Teri Orton said the rooftop terrace deck project alone has grown to at least $87 million, forcing officials to divert funds from other planned repairs.

As a result, HTA sought an additional $55 million in fiscal 2027. The request included $34 million in new capital improvement funds and permission to use $21 million from the agency’s enterprise fund, sourced from transient accommodations tax allocations and center revenue, according to HTA Vice President of Finance Talon Kishi.

Without the money, Orton said, repairs to other major leak sources — particularly the transom glass roof over the center concourse serving the third and fourth floors — would be delayed beyond the closure.

“If this project is not funded, the facility will reopen in 2028 with unresolved leaks that will continue to impact guest safety and overall experience,” Orton said. “This poses a significant risk to our reputation within the MCI (meetings, conventions and incentives) market and could lead to a decline in offshore bookings, which are critical to the state’s economic impact.”

Safety concerns have intensified as leaks worsen during heavy rainstorms. Orton said water intrusion has corroded steel support beams, damaged drywall and forced crews to place bins throughout the building during storms. During one conference, a section of drywall fell from the fourth floor to the third, narrowly missing attendees.

Orton said the center was nearing the point where rooms might have to close for safety before lawmakers approved the terrace deck replacement. Construction firm Swinerton began mobilizing in January after receiving a contract award in December.

During recent Kona‑low storms, she said Swinerton deployed sump pumps on the rooftop terrace deck and removed enough water to fill an Olympic‑size swimming pool.

Legislative scrutiny

Legislative skepticism has grown as costs rose. The rooftop repair was initially estimated at $51 million but climbed to $87 million — or $110.5 million with contingencies — due to longer timelines, rising labor and material costs, steel tariffs and more complete design documents.

Capital Improvement Project Chair Rep. Lisa Kitagawa (D-48, Kaneohe, Ahuimanu, Kahaluu, Waiahole, Kaaawa) has questioned whether repeated funding requests would ever fully resolve the leaks.

“After all the funding that the Legislature has given, will all of the leaking be completely fixed?” Kitagawa asked during a Jan. 16 informational briefing before the House Finance Committee.

Interim HTA President and CEO Caroline Anderson told lawmakers at the briefing that while the goal is to fix all known leaks, no agency can offer absolute guarantees for a complex, aging facility.

“This is a major building, and we cannot guarantee what will happen after,” Anderson said. “But our goal is to fix everything with what is appropriated.”

Orton told lawmakers that the rooftop terrace deck — which has not undergone a comprehensive repair in more than 20 years — is the primary source of the most severe water intrusion. She said additional projects proposed for fiscal 2027 would target other “front of house, client facing and leak related” areas that can be repaired while conventions are displaced.

Kitagawa pressed officials on whether approving the $55 million would end major repair requests. Orton replied that it would not, noting the center has planned projects through 2030 as part of its capital improvement plan.

Lawmakers also raised trust concerns over how previously appropriated funds were used. Kitagawa said $36 million authorized last year for other improvements was redirected to the rooftop terrace deck project without sufficient communication with lawmakers, while $15 million of earlier funding expired unused.

“What happened with just moving the funds is a breach of trust with the Legislature,” Kitagawa said. “I’m just concerned with if we do give you more additional funding, ‘How can we trust that it’s going to be utilized for what you say it’s going to be utilized for?’”

Anderson apologized to lawmakers, saying bid prices far exceeded early estimates and the urgency to fix the leaks necessitated moving ahead.

Sen. Sharon Moriwaki, vice chair of the Senate Ways and Means Committee, who handles capital improvements for the Senate, said she supports fixing the leaky rooftop terrace deck, but noted that lawmakers were assured that the earlier appropriation would be sufficient to cover contingencies.

Moriwaki (D-Waikiki, Ala Moana, Kakaako, McCully) emphasized that lawmakers last year also provided more money for other projects — repainting the interior, repairing slate tile, replacing carpeting, improving the sound system, upgrading digital signage and fixing escalators.

Moriwaki said she is particularly concerned that cost for the canopy, one facet of the rooftop terrace deck project, increased by millions, and in her view is not one of the center’s immediate needs. Financial records show that the canopy costs rose from $14 million to $21 million because of tariffs and the cost of steel to reinforce the weight.

“They came to us and we told them, ‘No’ and they still went ahead and contracted the canopy,” Moriwaki said. “To me it’s so unnecessary, they could use umbrellas over the tables. It’s really an over-the-top cost item.”

Kitagawa also raised concern during the briefing about the rooftop terrace deck project now including the canopy and other “extra beautiful things,” such as sound-proofing walls, grills and amenities for caterers. She added that, “when you don’t have a budget and you don’t have the money it’s very difficult for us, or for me, to say, ‘Hey let’s continue to give you more money,’ because you are not working within the budget and the agreed-upon expenses.”

Orton said the canopy cannot be added later to the rooftop terrace deck and that it would generate $4 million to $5 million annually in food and beverage sales, and raise the competitive profile of the center, which already contributes $45 million a year in taxes and hundreds of millions in visitor spending to the state’s tourism economy.

Moriwaki said she is not open to allocating new capital improvement funds to the center as the state’s financial picture has only gotten worse since the flooding and there already were “so many important state needs.”

“We already funded them to pay for the roof and building repairs and we will not appropriate any more CIP (capital improvement project) funds,” she said. “If they can pay for it via revenue bonds, we are open to that discussion.”

Kitagawa noted that she is open to further discussion with the Senate.

Bookings threatened

Tourism industry leaders warned last week that uncertainty over the project is already affecting future bookings.

Lynn Whitehead, vice president of MCI global sales and marketing for Meet Hawaiʻi, told the HTA advisory board on Wednesday that meeting planners and hotel executives said confidence in the facility’s readiness is critical as conventions make decisions for 2028 and beyond.

“We don’t want to open in 2028 and not be ready to welcome attendees,” Whitehead said.

Citywide conventions are booked years in advance, Whitehead said, and any doubts about completion timelines can slow or derail commitments — even as demand for Hawaii remains strong.

Whitehead told the HTA advisory board that Meet Hawai‘i had its strongest financial years before the center’s closure with 19 citywide events that filled 94,689 hotel room nights in 2024 and 21 citywide events that filled 159,187 hotel room nights in 2025.

She said a recovery milestone of 21 events has been set for 2028, when the center is slated to reopen. So far, she said that seven groups are confirmed for 2028.

Whitehead said by the end of June her team is working to close nine high-probability opportunities for 2028 and beyond, representing 80,000 hotel room nights and an estimated $280 million in economic impact.

“The window to secure 2028 business is active now, and decisions are being made,” she told the Honolulu Star-Advertiser.

Whitehead said her team is pursuing 48 active leads for convention center bookings between 2028 and 2033 that could bring an estimated 241,000 attendees who fill 438,000 hotel room nights and generate $1.5 billion in economic impact.

“We have worked hard to maintain transparency throughout this process and to build trust with our prospects and clients … Maintaining that confidence through clear communication and execution will be critical to converting business already in the pipeline,” she said.

FISCAL YEAR 2027 CAPITAL REPAIRS PLAN

The Hawai‘i Convention Center’s $55 million request covers 20 maintenance projects separate from the proposed rooftop terrace deck repair, which will cost at least $87 million, and could go up to $110.5 million with contingencies. While unrelated, the projects could be completed at the same time as the rooftop work — reducing future disruptions to convention business. The estimaed cost of the projects:

>> Ballroom gutter, foyer and lobby transom glass and soffit repair$22,123,054

>> Slate tile repair $1,575,000

>> House sound audio $5,381,306

>> Parking system equipment upgrade $1,050,000

>> Interior building painting $3,768,084

>> Digital signage upgrade $3,150,000

>> Carpet replacement $4,269,047

>> Air wall repairs, fabric replacement $1,396,944

>> Roll-up door replacement $211,411

>> IT network switch upgrade $346,500

>> Facility equipment replacement $760,342

>> ADA compliance, possibly other issues $171,450

>> Kalakaua kitchen boiler replacement $210,000

>> Cafe 808 renovation $2,715,508

>> Frictionless concession $1,665,508

>> 1801 renovation $3,870,704

>> Ice machines replacement $1,048,893

>> Loading dock supply fan replacement $236,250

>> Lobby door replacement $525,000

>> Xorel wall covering replacement $525,000

TOTAL $55 million

Source: HCC/HTA

ROOFTOP TERRACE DECK TIMELINE

Follow the timeline and progress of Hawai‘i Convention Center construction at 808ne.ws/41zNmgh

>> Jan. 2, 2026: Construction begins — HCC only open weekends and evenings

>> January-July: Phase I. Interior demolition, structural upgrades, canopy piers

>> July-February 2027: Phase 2. Rooftop canopy

>> February-June 2027: Phase 3. Reroofing

>> June- October 2027: Project completion

>> January 2028: HCC reopens

Source: HCC/HTA