Honolulu Star-Advertiser

Saturday, April 27, 2024 72° Today's Paper


Top News

Nightly H-1 lane closures start this week for concrete work

1/1
Swipe or click to see more

COURTESY HDOT

Crews will be installing an additional 128 precast concrete panels on the eastbound and westbound H-1 freeway near the Sears Distribution Center in Pearl City and on the eastbound H-1 freeway before the Aiea Heights Drive overpass, requiring overnight lane closures starting Wednesday evening.

A portion of the H-1 freeway in Pearl City and Aiea will be closed starting Thursday instead of Wednesday evening, as originally announced, for additional concrete panel work, according to the Hawaii Department of Transportation.

On Thursday, crews will be striping, and then in the following days, installing an additional 128 precast concrete panels on the eastbound H-1 freeway near the Sears Distribution Center in Pearl City and on the eastbound H-1 freeway before the Aiea Heights Drive overpass.

The closures have been updated to reflect only eastbound closures from Thursday to Sunday.

State officials said the closures are necessary in order to facilitate survey layout, saw cutting of existing pavement, and panel setting. These panels were not part of Phase 1 of the H-1 Shoulder and Portland Cement Concrete Pavement Rehabilitation (PCCP) project that rehabilitated rough asphalt segments of the freeway. For that phase, completed in mid-August, crews installed 1,279 precast concrete panels.

The installation of the additional panels is expected to be done in late November.

Lane closures are scheduled as follows:

THURSDAY TO FRIDAY

H-1 eastbound from the Pearl City Viaduct to the Aiea Pedestrian Overpass

>> Two left lanes closed from 6:30 p.m. to 4 a.m.

>> Additional left lane closed (for a total of three) from 7:30 p.m. to 4 a.m.

>> Shoulder will be open.

FRIDAY TO SATURDAY

H-1 eastbound from the Pearl City Viaduct to the Aiea Pedestrian Overpass

>> Two right lanes closed from 6:30 p.m. to 6:30 a.m.

>> Additional right lane closed (for a total of three) from 7:30 p.m. to 6 a.m.

>> Shoulder will not be available for vehicular traffic during the closure.

SATURDAY TO SUNDAY

H-1 eastbound from the Pearl City Viaduct to the Aiea Pedestrian Overpass

>> Two left lanes closed from 7 p.m. to 9 a.m.

>> Additional left lane closed (for a total of three) from 8 p.m. to 7:30 a.m.

>> Shoulder will be open.

H-1 eastbound from the vicinity of the Waimalu Viaduct to the Aiea Pedestrian Overpass

>> Shoulder closed from 9 a.m. to 7 p.m.

Motorists are advised to expect delays in the work zones during the nighttime closures. For updates on scheduled roadwork, please visit the HDOT website or follow its social media accounts on Facebook and Twitter.

By participating in online discussions you acknowledge that you have agreed to the Terms of Service. An insightful discussion of ideas and viewpoints is encouraged, but comments must be civil and in good taste, with no personal attacks. If your comments are inappropriate, you may be banned from posting. Report comments if you believe they do not follow our guidelines. Having trouble with comments? Learn more here.